Review Agenda Item
Meeting Date: 6/19/2018 - 7:00 PM
Category: SCHOOL FACILITIES MANAGEMENT
Type: Action
Subject: 22.29 CHANGE ORDER 1 for CAPITAL Contract 616597- CIP10458 “Upgrades to Electrical and HVAC Systems” DODSON SCHOOL for Plumbing Work to Mengler Mechanical, Inc., in the amount of $11,012.04, increasing the contract from $83,700.00 to $94,712.04 and extending the term to September 30, 2018 for paperwork purposes.
District Goals:
Enclosure
File Attachment:
Dodson - Mengler CO1 AIA form.pdf
BOCS MENGLER.xlsx
Dodson-Mengler Allow Utilization Summary.pdf
Res 16-7 Award Mengler - Dodson Plumbing 10458 12-16-15.pdf
Rationale: A change order is a written agreement between the District and its contractor to change a building construction contract. They add to, delete from, or otherwise alter the work and/or progress schedule in the contract bid documents. CO’s are caused by any of three situations that can arise on a project: unforeseen conditions, errors & omissions and owner directed extra work.

Delays in obtaining gas service from Con Edison has kept this contract open an additional 21 months.

There are four items of additional work valued at $26,012.04 of which $15,000 is being paid with contract contingencies leaving a balance of $11,012.04.

ITEM 1 - Unforseen Condition - for $1,817.53 paid by time and materials (T&M) to remove and cap a water line and a waste line under the nurse’s suite which was no longer needed and didn’t serve the space well.

ITEM 2 - Unforseen Condition - for $2,906.40 paid under T&M to replace 2 kitchen gas regulators which needed to be upgraded to high pressure use after Con Ed decided to upgrade their facilities.

ITEM 3 - Unforseen Condition – for $20,500 by under negotiated lump sum to replace two deteriorated gas supply trains. It was discovered that oil had been leaking into one train and deteriorating surfaces. The second was not functioning as required. E&R Engineering recommended that both trains be replaced at this time.

ITEM 4 – Owner Directed Extra – for $788.11 based solely on materials prices to upgrade the gas train safety fence enclosure to an 8 foot high, 1” black vinyl mesh fence & gate.
Funding: B5547CP110458.101438.B2204 $11,012.04 Local Capital Bond Fund
Resolution: Ladies and Gentlemen:

WHEREAS by Resolution Board Item No. 16.7 at the Board of Trustees stated meeting on December 16, 2015, contract No. 616597 was recommended for award to Mengler Mechanical, Inc, 1689 Route 22, Brewster, NY 10509, in the amount $83,700.00 and,

WHEREAS: in the course of executing the contracted work it was determined that additional work not fully covered by allowance was required to be performed in the amount of $11,012.04, increasing the overall cost of the contract from $83,700.00 to $94,712.04; and

WHEREAS a contract extension is required to be extend the contract to September 30, 2018 for completing this change order work, closeout documents and final payments.

NOW THEREFORE BE IT RESOLVED: That the Superintendent of Schools is hereby authorized to issue Change Order 1 to Contract 616597 Plumbing Contract, Project No. 10458 “Upgrades to Electrical and HVAC Systems” DODSON SCHOOL to Mengler Mechanical, Inc. in the amount of $11,012.04 increasing the contract amount from $83,700.00 to $94,712.04 and extending the contract to September 30, 2018.
Approvals:
Recommended By:
Signed By:
John Carr - Executive Director
Signed By:
Finance Department - Finance Reviewer
Signed By:
Elizabeth Janocha - Deputy Commissioner
Signed By:
John Liszewski - Commissioner
Signed By:
Matthew Gallagher - Corporation Counsel
Signed By:
Dr._Andrea_S. Coddett - Deputy Superintendent
Signed By:
Dr. Edwin M. Quezada - Superintendent of Schools
Vote Results:

Original Motion
Member Kevin Cacace Moved, Member Pasquale Mondesando seconded to approve the Original motion 'Ladies and Gentlemen:

WHEREAS by Resolution Board Item No. 16.7 at the Board of Trustees stated meeting on December 16, 2015, contract No. 616597 was recommended for award to Mengler Mechanical, Inc, 1689 Route 22, Brewster, NY 10509, in the amount $83,700.00 and,

WHEREAS: in the course of executing the contracted work it was determined that additional work not fully covered by allowance was required to be performed in the amount of $11,012.04, increasing the overall cost of the contract from $83,700.00 to $94,712.04; and

WHEREAS a contract extension is required to be extend the contract to September 30, 2018 for completing this change order work, closeout documents and final payments.

NOW THEREFORE BE IT RESOLVED: That the Superintendent of Schools is hereby authorized to issue Change Order 1 to Contract 616597 Plumbing Contract, Project No. 10458 “Upgrades to Electrical and HVAC Systems” DODSON SCHOOL to Mengler Mechanical, Inc. in the amount of $11,012.04 increasing the contract amount from $83,700.00 to $94,712.04 and extending the contract to September 30, 2018.'. Upon a Roll-Call Vote being taken, the vote was: Aye: 6 Nay: 0 Abstain: 1.
The motion Carried 6 - 0
   
Dr. Rosalba Corrado Del Vecchio     Yes
Andrea Brown     Yes
Kevin Cacace     Yes
Edgar Santana     Abstain
Rev. Steve Lopez     Yes
Judith_Ramos Meier     Yes
Pasquale Mondesando     Yes