Review Agenda Item
Meeting Date: 5/16/2018 - 7:00 PM
Category: SCHOOL FACILITIES MANAGEMENT
Type: Action
Subject: 19.2 AWARD of a CAPITAL FUND Construction Contract under and Emergency Declaration for CIP 10823 “WATER SERVICE BREAK REPAIR” at Cross Hill Academy to Peter J. Landi, Inc., in an amount not to exceed $22,703.42. Term is for 183 calendar days.
District Goals:
Enclosure
File Attachment:
Landi Proposals.pdf
Emergency Declaration Cross Hill Water Service Break Repair.pdf
BOCS Sheet Landi Cross Hill.xlsx
Rationale: This is to award a general construction contract as referenced above as per the attached emergency declaration issued by the Superintendent on December 11, 2017. Bids are not required under an emergency declaration.

Peter J. Landi, Inc. was selected by the Facilities Department because of their more than satisfactory history with the District. Peter J. Landi, Inc. occupied the site in December 2017 to repair the water main and restored associated site sidewalk and asphalt paving work during the February recess.
Funding: B5634CP110823.B17C01.B2206A1620, $22,703.42, LCBF
Resolution: Ladies and Gentlemen;

WHEREAS: An Emergency Declaration was issued on December 11, 2017 for Cross Hill Academy School “WATER SERVICE BREAK REPAIR”, and

WHEREAS: Under this emergency declaration the District solicited general construction work for the prompt repair of the water main break, and

WHEREAS: Peter J. Landi, Inc. indicated that they were capable and ready to make such emergency repair, and

WHEREAS: the District has a substantial successful history with Peter J. Landi, Inc., and

WHEREAS: Peter J. Landi, Inc., has indicated that the cost to the District of the work calculated and negotiated to date is not to exceed $22,703.42,

NOW THEREFORE BE IT RESOLVED: that the Superintendent of Schools is hereby authorized to award the above contract to Peter J. Landi, Inc., 13 Bradhurst Avenue, Hawthorne, NY 10532 in an amount not to exceed $22,703.42 for a term of 183 calendar days.
Approvals:
Recommended By:
Signed By:
John Carr - Executive Director
Signed By:
Tom Collich - Purchasing Director
Signed By:
Finance Department - Finance Reviewer
Signed By:
Elizabeth Janocha - Deputy Commissioner
Signed By:
John Liszewski - Commissioner
Signed By:
Michael Curti - Corporation Counsel
Signed By:
Dr._Andrea_S. Coddett - Deputy Superintendent
Signed By:
Dr. Edwin M. Quezada - Superintendent of Schools
Vote Results:

Original Motion
Member Kevin Cacace Moved, Member Judith_Ramos Meier seconded to approve the Original motion 'Ladies and Gentlemen;

WHEREAS: An Emergency Declaration was issued on December 11, 2017 for Cross Hill Academy School “WATER SERVICE BREAK REPAIR”, and

WHEREAS: Under this emergency declaration the District solicited general construction work for the prompt repair of the water main break, and

WHEREAS: Peter J. Landi, Inc. indicated that they were capable and ready to make such emergency repair, and

WHEREAS: the District has a substantial successful history with Peter J. Landi, Inc., and

WHEREAS: Peter J. Landi, Inc., has indicated that the cost to the District of the work calculated and negotiated to date is not to exceed $22,703.42,

NOW THEREFORE BE IT RESOLVED: that the Superintendent of Schools is hereby authorized to award the above contract to Peter J. Landi, Inc., 13 Bradhurst Avenue, Hawthorne, NY 10532 in an amount not to exceed $22,703.42 for a term of 183 calendar days.'. Upon a Roll-Call Vote being taken, the vote was: Aye: 6 Nay: 0 Abstain: 1.
The motion Carried 6 - 0
   
Pasquale Mondesando     Yes
Edgar Santana     Abstain
Dr. Rosalba Corrado Del Vecchio     Yes
Kevin Cacace     Yes
Judith_Ramos Meier     Yes
John Jacono     Yes
Rev. Steve Lopez     Yes