Meeting Date:
|
6/19/2019 - 7:00 PM
|
Category:
|
SCHOOL FACILITIES MANAGEMENT
|
Type:
|
Action
|
Subject:
|
21.43 AMENDMENT to the Assignment of Environmental Services Task for CIP 10811 “AHERA Asbestos Management Plan Remediation” at School 21, to Contract No. 618430, PO 2018-5307, with LiRo Engineers, Inc., in the amount of $9,757.00, revising their existing assignment from $21,400.00 to $31,157.00 and extend the PO for an additional 365 days.
|
District Goals:
|
|
Enclosure
|
|
File Attachment:
|
|
Rationale:
|
Via Resolution 17.16 at their stated meeting on May 17, 2017 the Board of Trustees approved the subject assignment to LiRo Engineers, Inc. in the amount of $21,400. This is to increase the LiRo Engineer’s fee by $9,757.00 to provide added design, bidding & negotiating, additional environmental project monitoring and construction support services for the additional abatement of asbestos insulation and re-insulating of building heating pipes.
|
Funding:
|
B5521CP110811.B17C01.B2040A1620, $9,757.00, Local Capital Bonded Fund
|
Resolution:
|
Ladies and Gentlemen: WHEREAS: Via Resolution 17.16 at their stated meeting on May 17, 2017 the Board of Trustees approved the subject assignment to LiRo Engineers Inc. in the amount of $21,400 WHEREAS: additional professional Environmental Services for CIP 10811, “Asbestos Management Plan Remediation” at School 21 was required of LiRo Engineers, Inc. in the amount not to exceed $9,757.00, increasing the fee for this assignment from $21,400 to $31,157.00 and extending the duration of the contract by 365 calendar days. NOW THEREFORE BE IT RESOLVED: That the Superintendent of Schools is hereby authorized to amend PO 2018-5307 with LiRo Engineers, Inc.3 Aerial Way, Syosset, NY 11792 to provide additional professional Environmental services for CIP 10811“Asbestos Management Plan Remediation” at School 21”, Contract No. 618430, PO 2018-5307 in an amount not to exceed $9,757.00 increasing the fee for this assignment from $21,400 to $31,157.00 and extending the PO duration by 365 calendar days.
|
Approvals:
|
Recommended By:
|
Signed By:
|
|
John Carr - Executive Director
|
|
Signed By:
|
|
Lee Pavone - Mechanical Engineer
|
|
Signed By:
|
|
Tom Collich - Purchasing Director
|
|
Signed By:
|
|
Finance Department - Finance Reviewer
|
|
Signed By:
|
|
Elizabeth Janocha - Deputy Commissioner
|
|
Signed By:
|
|
John Liszewski - Commissioner
|
|
Signed By:
|
|
Matthew Gallagher - Corporation Counsel
|
|
Signed By:
|
|
Dr._Andrea_S. Coddett - Deputy Superintendent
|
|
Signed By:
|
|
Dr. Edwin M. Quezada - Superintendent of Schools
|
|
|
|
Vote Results:
|
Original Motion | Member Kevin Cacace Moved, Member Dr._Ammir Rabadi seconded to approve the Original motion 'Ladies and Gentlemen: WHEREAS: Via Resolution 17.16 at their stated meeting on May 17, 2017 the Board of Trustees approved the subject assignment to LiRo Engineers Inc. in the amount of $21,400 WHEREAS: additional professional Environmental Services for CIP 10811, “Asbestos Management Plan Remediation” at School 21 was required of LiRo Engineers, Inc. in the amount not to exceed $9,757.00, increasing the fee for this assignment from $21,400 to $31,157.00 and extending the duration of the contract by 365 calendar days. NOW THEREFORE BE IT RESOLVED: That the Superintendent of Schools is hereby authorized to amend PO 2018-5307 with LiRo Engineers, Inc.3 Aerial Way, Syosset, NY 11792 to provide additional professional Environmental services for CIP 10811“Asbestos Management Plan Remediation” at School 21”, Contract No. 618430, PO 2018-5307 in an amount not to exceed $9,757.00 increasing the fee for this assignment from $21,400 to $31,157.00 and extending the PO duration by 365 calendar days.'. Upon a Roll-Call Vote being taken, the vote was: Aye: 6 Nay: 0. | The motion Carried 6 - 0 | | | Judith_Ramos Meier | Yes | Rev. Steve Lopez | Yes | Andrea Brown | Yes | Kevin Cacace | Yes | Dr. Rosalba Corrado Del Vecchio | Yes | Dr._Ammir Rabadi | Yes | |
|
|
|
|
|
|