Subject: 20.15 CHANGE ORDER 1 (CREDIT) for CAPITAL Contract 2018-00000745, Contract 4 of 5, PLUMBING WORK, CIP10745 “Reconstruction of Portions of the Building Envelope, Interior Finishes and Site Work” at Paideia School 24 to Joseph Lombardo Plumbing and Heating, for a credit in the amount of $20,000, decreasing the contract amount from $36,589 to $16,589.
District Goals:
Enclosure
File Attachment:
BOE Resolution PS-24 HVAC Lombardo.pdf
LOMBARDO HVAC CREDIT CO1 AIA.pdf
Copy of BOCS LOMBARDO PS24 PLUMB.pdf
Rationale: A change order is a written agreement between the District and its contractor to change a building construction contract. They add to, delete from, or otherwise alter the work and/or progress schedule in the contract bid documents. CO’s are caused by any of three situations that can arise on a project: unforeseen conditions, design errors and omissions and owner directed extra work.

This is a credit Change Order of $20,000.00 for the entire remaining balance to a $20,000.00 allowance of any additional work in the contract.

There were no owner requested extra work in this contract.
Funding: B5524CP110745.B17C01.B2204A1620 <$20,000.00> CREDIT
Resolution: Ladies and Gentlemen:

WHEREAS by Resolution Board Item No. 18.9 at the Board of Trustees stated meeting on December 20, 2017, contract No. 2018-00000745 was recommended for award to Joseph Lombardo Plumbing and Heating, 321 Spook Rock Road, Suffern, NY 10909 and,

WHEREAS: in the course of executing the contracted work it was determined that additional allowance work was not required to be performed for a credit in the amount of $20,000.00, decreasing the overall cost of the contract from $36,589.00 to $16,589.00.

NOW THEREFORE BE IT RESOLVED: That the Superintendent of Schools is hereby authorized to issue Change Order 1 to contract No. 2018-00000745, Plumbing Construction Contract, CIP10745, “Reconstruction of Portions of the Building Envelope, Interior Finishes and Site Work” at Paideia School 24 to Joseph Lombardo Plumbing and Heating for a CREDIT in the amount of $20,000.00, decreasing the overall cost of the contract from $36,589.00 to $16,589.00.
Approvals:
Recommended By:
Signed By:
John Carr - Executive Director
Signed By:
Tom Collich - Purchasing Director
Signed By:
Finance Department - Finance Reviewer
Signed By:
Elizabeth Janocha - Deputy Commissioner
Signed By:
Matthew Gallagher - Corporation Counsel
Signed By:
Dr._Andrea_S. Coddett - Deputy Superintendent
Signed By:
Dr. Edwin M. Quezada - Superintendent of Schools
Vote Results:

Original Motion
Member Kevin Cacace Moved, Member Pasquale Mondesando seconded to approve the Original motion 'Ladies and Gentlemen:

WHEREAS by Resolution Board Item No. 18.9 at the Board of Trustees stated meeting on December 20, 2017, contract No. 2018-00000745 was recommended for award to Joseph Lombardo Plumbing and Heating, 321 Spook Rock Road, Suffern, NY 10909 and,

WHEREAS: in the course of executing the contracted work it was determined that additional allowance work was not required to be performed for a credit in the amount of $20,000.00, decreasing the overall cost of the contract from $36,589.00 to $16,589.00.

NOW THEREFORE BE IT RESOLVED: That the Superintendent of Schools is hereby authorized to issue Change Order 1 to contract No. 2018-00000745, Plumbing Construction Contract, CIP10745, “Reconstruction of Portions of the Building Envelope, Interior Finishes and Site Work” at Paideia School 24 to Joseph Lombardo Plumbing and Heating for a CREDIT in the amount of $20,000.00, decreasing the overall cost of the contract from $36,589.00 to $16,589.00.'. Upon a Roll-Call Vote being taken, the vote was: Aye: 6 Nay: 0 Abstain: 1.
The motion Carried 6 - 0
   
Judith_Ramos Meier     Yes
Rev. Steve Lopez     Yes
Pasquale Mondesando     Yes
Edgar Santana     Abstain
Dr. Rosalba Corrado Del Vecchio     Yes
Kevin Cacace     Yes
Andrea Brown     Yes