Review Agenda Item
Meeting Date: 4/18/2018 - 7:00 PM
Category: SCHOOL FACILITIES MANAGEMENT
Type: Action
Subject: 20.12 CHANGE ORDER 1 for CAPITAL Contract 616304, CIP10572, “Reconstruction of Windows, Doors, Roof and Arena Features” at YONKERS MIDDLE HIGH SCHOOL to Arrow Steel Window Corp., for the amount of $7,369.00, increasing the contract amount from $2,894,000.00 to $2,901,369.00 and extending the contract term to September 30, 2018.
District Goals:
Enclosure
File Attachment:
BOCS Sheet YMHS ASW.xlsx
BOE Resolution Agenda Item 16.16 12-16-2015.pdf
Change Order 1 AIA Form & SED Form & GC Proposal.pdf
Rationale: A change order is a written agreement between the District and its contractor to change a building construction contract. They add to, delete from, or otherwise alter the work and/or progress schedule in the contract bid documents. CO’s are caused by any of three situations that can arise on a project: unforeseen conditions, design errors and omissions and owner directed extra work.

This change order is for District directed additional work to furnish and install 14 new locks on 14 existing doors that could only be unlocked from the inside of the room. This arrangement is of great benefit to the operation of the building.

The contract term is being re-scheduled to September 30, 2018 for closeout paperwork.
Funding: B5742CP110572.101256.B2200 $7,369.00 Local Capital Bonded Fund
Resolution: Ladies and Gentlemen:

WHEREAS by Resolution Board Item No. 16.16 at the Board of Trustees stated meeting on December 16, 2015, contract No. 616304 was recommended for award to Arrow Steel Window Corp., and,

WHEREAS: in the course of executing the contracted work it was determined that additional work was required to be performed for the negotiated lumps sum of $7,369.00, for owner directed extra work increasing the overall cost of the contract from $2,894,000.00 to 2,901,369.00;

WHEREAS: the contract requires an extension to September 30, 2018 for completing final closeout and payments.

NOW THEREFORE BE IT RESOLVED: That the Superintendent of Schools is hereby authorized to issue Change Order 1 to Contract 616304, General Construction Windows & Doors Contract, Project No. 10572 Reconstruction of Windows, Doors, Roof and Arena Features” at YONKERS MIDDLE HIGH SCHOOL to Arrow Steel Window Corp. for the amount of $7,369.00 increasing the contract amount from $2,894,000.00 to 2,901,369.00.

LABOR UNION: No
Approvals:
Recommended By:
Signed By:
John Carr - Executive Director
Signed By:
Tom Collich - Purchasing Director
Signed By:
Finance Department - Finance Reviewer
Signed By:
Elizabeth Janocha - Deputy Commissioner
Signed By:
John Liszewski - Commissioner
Signed By:
Michael Curti - Corporation Counsel
Signed By:
Dr. Fenix Arias - Manager of Administration
Signed By:
Dr._Andrea_S. Coddett - Deputy Superintendent
Signed By:
Dr. Edwin M. Quezada - Superintendent of Schools
Vote Results:

Original Motion
Member Kevin Cacace Moved, Member Edgar Santana seconded to approve the Original motion 'Ladies and Gentlemen:

WHEREAS by Resolution Board Item No. 16.16 at the Board of Trustees stated meeting on December 16, 2015, contract No. 616304 was recommended for award to Arrow Steel Window Corp., and,

WHEREAS: in the course of executing the contracted work it was determined that additional work was required to be performed for the negotiated lumps sum of $7,369.00, for owner directed extra work increasing the overall cost of the contract from $2,894,000.00 to 2,901,369.00;

WHEREAS: the contract requires an extension to September 30, 2018 for completing final closeout and payments.

NOW THEREFORE BE IT RESOLVED: That the Superintendent of Schools is hereby authorized to issue Change Order 1 to Contract 616304, General Construction Windows & Doors Contract, Project No. 10572 Reconstruction of Windows, Doors, Roof and Arena Features” at YONKERS MIDDLE HIGH SCHOOL to Arrow Steel Window Corp. for the amount of $7,369.00 increasing the contract amount from $2,894,000.00 to 2,901,369.00.

LABOR UNION: No'. Upon a Roll-Call Vote being taken, the vote was: Aye: 8 Nay: 0.
The motion Carried 8 - 0
   
Judith_Ramos Meier     Yes
Rev. Steve Lopez     Yes
John Jacono     Yes
Pasquale Mondesando     Yes
Kevin Cacace     Yes
Edgar Santana     Yes
Andrea Brown     Yes
Dr. Rosalba Corrado Del Vecchio     Yes