Meeting Date:
|
8/21/2019 - 6:30 PM
|
Category:
|
SCHOOL FACILITIES MANAGEMENT
|
Type:
|
Action
|
Subject:
|
15.6 AWARD of a CAPITAL FUND Construction Contract under Emergency Declaration for CIP 10857, “Roof Wind Damage Repairs” at the Roosevelt High School to Best Climate Control Corp., in an amount not to exceed $7,668.71. Term is for 183 calendar days.
|
District Goals:
|
|
Enclosure
|
|
File Attachment:
|
|
Rationale:
|
This is to award a mechanical construction contract as referenced above as per the attached emergency declaration issued by the Superintendent on February 26, 2019. Bids are not required under an emergency declaration. Best Climate Control Corp. was selected by the School Facilities Management Department (SFM) because they have a standing service contract and satisfactory history with the District. Services provided include upgrades the AC equipment mounting, refrigerant piping and commissioning. This damage to the AC unit was due to the high winds that lifted a portion of the roof as per the attached Emergency Declaration.
|
Funding:
|
B5755CP110857.B18C02.B2203A1620, $7,668.71, Cash Capital
|
Resolution:
|
Ladies and Gentlemen; WHEREAS: An Emergency Declaration was issued on February 26, 2019 for the “Roof Wind Damage Repairs” at the Roosevelt High School and WHEREAS: Under this emergency declaration the District solicited HVAC construction work for the prompt repairs to the roof top AC Unit, and WHEREAS: Best Climate Control Corp. indicated that they were capable and ready to make such repairs in the shortest time frame, and WHEREAS: the District has a substantial successful history with Best Climate Control Corp., and WHEREAS: Best Climate Control Corp. has indicated that the maximum cost to the District of the work that they are directed to perform is not to exceed $7,668.71, NOW THEREFORE BE IT RESOLVED: that the Superintendent of Schools is hereby authorized to award the above contract to Best Climate Control Corp., 75 Orville Dr., Bohemia, NY 11716, 1689 Route 22, Brewster, NY 10509 in the amount of $7,668.71 for a term of 183 calendar days.
|
Approvals:
|
Recommended By:
|
Signed By:
|
|
John Carr - Executive Director
|
|
Signed By:
|
|
Finance Department - Finance Reviewer
|
|
Signed By:
|
|
Tom Collich - Purchasing Director
|
|
Signed By:
|
|
Elizabeth Janocha - Deputy Commissioner
|
|
Signed By:
|
|
John Liszewski - Commissioner
|
|
Signed By:
|
|
Matthew Gallagher - Corporation Counsel
|
|
Signed By:
|
|
Dr._Andrea_S. Coddett - Deputy Superintendent
|
|
Signed By:
|
|
Dr. Edwin M. Quezada - Superintendent of Schools
|
|
|
|
Vote Results:
|
Original Motion | Member Kevin Cacace Moved, Member Abdool H. Jamal seconded to approve the Original motion 'Ladies and Gentlemen; WHEREAS: An Emergency Declaration was issued on February 26, 2019 for the “Roof Wind Damage Repairs” at the Roosevelt High School and WHEREAS: Under this emergency declaration the District solicited HVAC construction work for the prompt repairs to the roof top AC Unit, and WHEREAS: Best Climate Control Corp. indicated that they were capable and ready to make such repairs in the shortest time frame, and WHEREAS: the District has a substantial successful history with Best Climate Control Corp., and WHEREAS: Best Climate Control Corp. has indicated that the maximum cost to the District of the work that they are directed to perform is not to exceed $7,668.71, NOW THEREFORE BE IT RESOLVED: that the Superintendent of Schools is hereby authorized to award the above contract to Best Climate Control Corp., 75 Orville Dr., Bohemia, NY 11716, 1689 Route 22, Brewster, NY 10509 in the amount of $7,668.71 for a term of 183 calendar days.'. Upon a Roll-Call Vote being taken, the vote was: Aye: 5 Nay: 0. | The motion Carried 5 - 0 | | | Rev. Steve Lopez | Yes | Kevin Cacace | Yes | Dr._Ammir Rabadi | Yes | Dr. Rosalba Corrado Del Vecchio | Yes | Abdool H. Jamal | Yes | |
|
|
|
|
|
|