Review Agenda Item
Meeting Date: 6/19/2018 - 7:00 PM
Category: SCHOOL FACILITIES MANAGEMENT
Type: Action
Subject: 22.8 Amendment of Assignment of Architectural Services for CAPITAL Project 10824, “Select Roof and Masonry Repair” at Lincoln High School, Contract 617160 to KG+D Architects, PC in the amount of $10,000.00 for reimbursable expenses for a term of 365 days.
District Goals:
Enclosure
File Attachment:
BOE - Resolution approval- 3-22-2018.pdf
KG+D Proposal.pdf
Rationale: Via Resolution 16.11 at their stated meeting on March 22, 2018 the Board of Trustees awarded the above subject assignment to KG+D in the amount of $30,000.00. Unfortunately the work required for the handling of asbestos containing building materials (ACBM) was inadvertently omitted from that task and has to be included under this amendment. The upset cost for his work is anticipated to be up to $10,000 for sampling, testing and the design for the amelioration of ACBM issue, if any. This is a direct reimbursement for services by others with no mark-up.

The scope of work for CIP10824 includes but is not necessarily limited to the roof, masonry façade, interior finishes and related asbestos abatement in the vicinity of Stairwell ”A” at the north west corner of the building. Project cost is estimated to be $230,000 to $250,000. Construction is anticipated to take place in late summer or fall of 2018.
Funding: B5751CP110824.B17C01.B2046A1620 Local Capital Bonded Fund
Resolution: Ladies and Gentlemen:

WHEREAS: under Resolution 17.5 at the stated meeting on January 20, 2016, the Board of Education authorized the award of a requirements based, professional Architectural/Engineering services contract to KG&D Architects in response to District RFQ313 “Architectural & Engineering Services for the School Facilities Management Department” for an amount not to exceed $1 million, amended on June 20, 2017 to increase the original agreement by $500,000.00 for a total amount not to exceed $1,500,000.00 and

WHEREAS: work as defined under that contract is required for capital project 10824 “Select Roof and Masonry Repair” at Lincoln High School, and

WHEREAS: an amendment is required to include additional services to the CIP 10824,

NOW THEREFORE BE IT RESOLVED: That the Superintendent of Schools is hereby authorized to appoint KG&D Architects, 285 Main Street, Mt. Kisco, New York 10549, to the task of providing professional Architectural/Engineering for the capital project 10824 “Select Roof And Masonry Repair” at Lincoln High School for an additional amount of $10,000.00 increasing the contract amount to $40,000.00 effective June 20, 2018 under Contract No. 617160, “Architectural & Engineering Services for the School Facilities Management Department”.
Approvals:
Recommended By:
Signed By:
John Carr - Executive Director
Signed By:
Tom Collich - Purchasing Director
Signed By:
Finance Department - Finance Reviewer
Signed By:
Elizabeth Janocha - Deputy Commissioner
Signed By:
John Liszewski - Commissioner
Signed By:
Matthew Gallagher - Corporation Counsel
Signed By:
Dr. Fenix Arias - Manager of Administration
Signed By:
Dr._Andrea_S. Coddett - Deputy Superintendent
Signed By:
Dr. Edwin M. Quezada - Superintendent of Schools
Vote Results:

Original Motion
Member Kevin Cacace Moved, Member Pasquale Mondesando seconded to approve the Original motion 'Ladies and Gentlemen:

WHEREAS: under Resolution 17.5 at the stated meeting on January 20, 2016, the Board of Education authorized the award of a requirements based, professional Architectural/Engineering services contract to KG&D Architects in response to District RFQ313 “Architectural & Engineering Services for the School Facilities Management Department” for an amount not to exceed $1 million, amended on June 20, 2017 to increase the original agreement by $500,000.00 for a total amount not to exceed $1,500,000.00 and

WHEREAS: work as defined under that contract is required for capital project 10824 “Select Roof and Masonry Repair” at Lincoln High School, and

WHEREAS: an amendment is required to include additional services to the CIP 10824,

NOW THEREFORE BE IT RESOLVED: That the Superintendent of Schools is hereby authorized to appoint KG&D Architects, 285 Main Street, Mt. Kisco, New York 10549, to the task of providing professional Architectural/Engineering for the capital project 10824 “Select Roof And Masonry Repair” at Lincoln High School for an additional amount of $10,000.00 increasing the contract amount to $40,000.00 effective June 20, 2018 under Contract No. 617160, “Architectural & Engineering Services for the School Facilities Management Department”.'. Upon a Roll-Call Vote being taken, the vote was: Aye: 6 Nay: 0 Abstain: 1.
The motion Carried 6 - 0
   
Judith_Ramos Meier     Yes
Rev. Steve Lopez     Yes
Edgar Santana     Abstain
Pasquale Mondesando     Yes
Andrea Brown     Yes
Kevin Cacace     Yes
Dr. Rosalba Corrado Del Vecchio     Yes