Review Agenda Item
Meeting Date: 2/27/2019 - 7:00 PM
Category: SCHOOL FACILITIES MANAGEMENT
Type: Action
Subject: 18.10 DEFAULT of CAPITAL Construction Contract 2018-00000796 GENERAL CONSTRUCTION CIP10656 “Reconstruction of Portions of the Exterior Envelope, Select Interior Finishes and HVAC Systems” at Gorton High School with Dobtol Construction LLC.
District Goals:
Enclosure
File Attachment:
NTP Gorton Dobtol.pdf
1st Notice of Default DOBTOL .pdf
Dobtol Award Res.pdf
BOCS DOBTOL.xlsx
Rationale: This is to authorize the initiation and completion of default proceedings against DOBTOL Construction, LLC., in compliance with Articles 38 “YPS Right to Declare Contractor in Default” and 40 “Exercise of the Right to Declare Default” of the contract.

The above contract was awarded by the Board of Trustees via Board Item 20.7 at their stated meeting on April 18, 2018. A notice to proceed was issued to DOBTOL on May 7, 2018. Work commenced and proceeded with some problems until late August where it became apparent that DOBTOL was not able to complete certain aspects of the contract, most notably the exterior doors at a rate needed to complete the construction work as per the contract schedule. Payment by DOBTOL to suppliers and subcontractors has also been an issue.

This default process has been undertaken under the advice of the Corporation Counsel’s office and Fuller and D’Angelo Architects, PC., serving as both designer and construction managers. The administration will be making claims against the performance and labor bonds for the completion of the work.

The original contract amount is $1,934,186.00 the amount authorized for payment to date is $1,621,236.00. The outstanding work includes but is not necessarily limited to the furnishing and installation of all of the building exterior doors.
Funding: NOT APPLICABLE
Resolution: Ladies and Gentlemen:

WHEREAS: CAPITAL Contract 2018-00000796 GENERAL CONSTRUCTION Work for CIP10656 “Reconstruction of Portions of the Exterior Envelope, Select Interior Finishes and HVAC Systems” at Gorton High School was awarded to WITH Dobtol Construction LLC via Board Item 20.7 at the Board of Trustees stated meeting on May 7, 2018, and

WHEREAS: work by the contractor consistently failed to meet contract specifications in terms of work performed and adherence to the scheduled, and

WHEREAS: the late date and the nature of the unacceptable work jeopardized the building integrity and the timely opening of school, and

WHEREAS: all reasonable means were taken by the District and their representative Fuller and D’Angelo Architects, PC to correct such deficiencies, and

WHEREAS: despite all such efforts it was determined that DOBTOL Construction, LLC., was incapable of completing the outstanding unaccepted work under this contract, and

WHEREAS: a Notice of Intent to Default was issued to DOBTOL on January 31, 2019, and

WHEREAS: : a second Notice of Intent to Default was issued to DOBTOL on February 9, 2019 wherein it is confirmed that DOBTOL is incapable of completing any more physical work on this project and that they are relinquishing such to their Surety.

NOW THEREFORE BE IT RESOLVED: that Contract 2018-00000796 GENERAL CONSTRUCTION CIP10656 “Reconstruction of Portions of the Exterior Envelope, Select Interior Finishes and HVAC Systems” at Gorton High School with DOBTOL Construction LLC be defaulted and that the Yonkers Public Schools use any and all means legally available to enforce the contract to complete the work therein.
Approvals:
Recommended By:
Signed By:
John Carr - Executive Director
Signed By:
Tom Collich - Purchasing Director
Signed By:
Finance Department - Finance Reviewer
Signed By:
Elizabeth Janocha - Deputy Commissioner
Signed By:
John Liszewski - Commissioner
Signed By:
Matthew Gallagher - Corporation Counsel
Signed By:
Dr._Andrea_S. Coddett - Deputy Superintendent
Signed By:
Dr. Edwin M. Quezada - Superintendent of Schools
Vote Results:

Original Motion
Member Kevin Cacace Moved, Member Edgar Santana seconded to approve the Original motion 'Ladies and Gentlemen:

WHEREAS: CAPITAL Contract 2018-00000796 GENERAL CONSTRUCTION Work for CIP10656 “Reconstruction of Portions of the Exterior Envelope, Select Interior Finishes and HVAC Systems” at Gorton High School was awarded to WITH Dobtol Construction LLC via Board Item 20.7 at the Board of Trustees stated meeting on May 7, 2018, and

WHEREAS: work by the contractor consistently failed to meet contract specifications in terms of work performed and adherence to the scheduled, and

WHEREAS: the late date and the nature of the unacceptable work jeopardized the building integrity and the timely opening of school, and

WHEREAS: all reasonable means were taken by the District and their representative Fuller and D’Angelo Architects, PC to correct such deficiencies, and

WHEREAS: despite all such efforts it was determined that DOBTOL Construction, LLC., was incapable of completing the outstanding unaccepted work under this contract, and

WHEREAS: a Notice of Intent to Default was issued to DOBTOL on January 31, 2019, and

WHEREAS: : a second Notice of Intent to Default was issued to DOBTOL on February 9, 2019 wherein it is confirmed that DOBTOL is incapable of completing any more physical work on this project and that they are relinquishing such to their Surety.

NOW THEREFORE BE IT RESOLVED: that Contract 2018-00000796 GENERAL CONSTRUCTION CIP10656 “Reconstruction of Portions of the Exterior Envelope, Select Interior Finishes and HVAC Systems” at Gorton High School with DOBTOL Construction LLC be defaulted and that the Yonkers Public Schools use any and all means legally available to enforce the contract to complete the work therein.'. Upon a Roll-Call Vote being taken, the vote was: Aye: 8 Nay: 0.
The motion Carried 8 - 0
   
Rev. Steve Lopez     Yes
Judith_Ramos Meier     Yes
Andrea Brown     Yes
Pasquale Mondesando     Yes
Edgar Santana     Yes
Kevin Cacace     Yes
Dr. Rosalba Corrado Del Vecchio     Yes
Dr._Ammir Rabadi     Yes