Review Agenda Item
Meeting Date: 4/17/2024 - 5:30 PM
Category: SCHOOL FACILITIES MANAGEMENT
Type: Action
Subject: 18.5 Fuller and D’Angelo, P.C. Architects & Planners (CIP 10953, 10954, 10955 & 10956) - Amendment 3
District Goals:
Enclosure
File Attachment:
F&D Phase II Proposal Summary.pdf
F&D RFP Response.pdf
RES 15.6 11.16.2022.pdf
Rationale: Fuller and D’Angelo, P.C. Architects & Planners
Amount: $83,200.00
Scope: To provide additional architectural and engineering services for the “Phase II Building Upgrades” work under Capital Projects 10953, 10954, 10955 & 10956, “Playgrounds & Building Upgrades” at Montessori School 27, Kahlil Gibran School, Westchester Hills School 29 & Paideia School 15. This includes development of a separate bid package for Phase II work, provide bidding and negotiation, and construction administration services.

Overview:
This amendment is to cover the cost for work not included in the original award for bidding and negotiation, and construction administration services for the Phase II building upgrades work. (RES 15.6 dated November 16, 2022).

Phase I is for the playground and site upgrades at Montessori School 27, Kahlil Gibran School, Westchester Hills School 29 and Paideia School 15, scheduled to be completed by spring of 2024 at a cost of $1.3 million.

Phase II work scheduled for summer 2024 is estimated to be $3.1 million and includes;

-Montessori School 27 CIP 10953: new fire alarm, PA system, replacement of corridor ceilings & lights and improvements to the main entrance.
-Kahlil Gibran School CIP 10954: new fire alarm system.
-Westchester Hills School 29 CIP 10955: new fire alarm system.
-Paideia School 15 CIP 10956: new gym floor, lighting, doors and finishes.
Funding: B5527CP110953.B24C01.B2046A1620, $25,600.00, LCBF
B5528CP110954.B24C01.B2046A1620, $19,200.00, LCBF
B5529CP110955.B24C01.B2046A1620, $19,200.00, LCBF
B5515CP110956.B24C01.B2046A1620, $19,200.00, LCBF
Resolution: WHEREAS via Resolution 15.6 dated November 16, 2022, the Board of Education awarded Purchase Order 2023-4875 Architectural Services for CIP 10953, 10954, 10955 & 10956 “Playground & Select Building Upgrades" at Montessori School 27, Kahlil Gibran School, Westchester Hills School 29 and Paideia School 15 to Fuller & D’Angelo P.C., (F&D) in the amount of $215,560.00 and a term of 365 calendar days under Contract 2020-0628, and

WHEREAS additional architectural services are required for the “Phase II Building Upgrades” work under Capital Projects 10953, 10954, 10955 & 10956, “Playgrounds & Building Upgrades” at Montessori School 27, Kahlil Gibran School, Westchester Hills School 29 & Paideia School 15, and

WHEREAS F&D has presented an acceptable proposal to complete this added task for developing a separate bid package, bidding and negotiation, and construction administration services for the Phase II “Building Upgrades” at a cost of $83,200.00, and

NOW THEREFORE BE IT RESOLVED: That the Board of Education hereby authorizes the Superintendent of Schools to amend the existing assignment for CIP 10953, 10954, 10955 & 10956 “Playground & Select Building Upgrades" at Montessori School 27, Kahlil Gibran School, Westchester Hills School 29 and Paideia School 15 under Contract 2020-0628 to Fuller & D’Angelo P.C. for $83,200.00, increasing the assignment amount from $260,260.00 to $343,460.00.
Approvals:
Recommended By:
Signed By:
Michael Pelliccio - Director of Facilities III
Signed By:
Tom Collich - Purchasing Director
Signed By:
Finance Department - Finance Reviewer
Signed By:
Elizabeth Janocha - Deputy Commissioner
Signed By:
John Liszewski - Commissioner
Signed By:
Matthew Gallagher - Corporation Counsel
Signed By:
Dr. Luis Rodriguez - Interim Superintendent of Schools
Vote Results:

Original Motion
Member Dr. John Castanaro Moved, Member Kevin Cacace seconded to approve the Original motion 'WHEREAS via Resolution 15.6 dated November 16, 2022, the Board of Education awarded Purchase Order 2023-4875 Architectural Services for CIP 10953, 10954, 10955 & 10956 “Playground & Select Building Upgrades" at Montessori School 27, Kahlil Gibran School, Westchester Hills School 29 and Paideia School 15 to Fuller & D’Angelo P.C., (F&D) in the amount of $215,560.00 and a term of 365 calendar days under Contract 2020-0628, and

WHEREAS additional architectural services are required for the “Phase II Building Upgrades” work under Capital Projects 10953, 10954, 10955 & 10956, “Playgrounds & Building Upgrades” at Montessori School 27, Kahlil Gibran School, Westchester Hills School 29 & Paideia School 15, and

WHEREAS F&D has presented an acceptable proposal to complete this added task for developing a separate bid package, bidding and negotiation, and construction administration services for the Phase II “Building Upgrades” at a cost of $83,200.00, and

NOW THEREFORE BE IT RESOLVED: That the Board of Education hereby authorizes the Superintendent of Schools to amend the existing assignment for CIP 10953, 10954, 10955 & 10956 “Playground & Select Building Upgrades" at Montessori School 27, Kahlil Gibran School, Westchester Hills School 29 and Paideia School 15 under Contract 2020-0628 to Fuller & D’Angelo P.C. for $83,200.00, increasing the assignment amount from $260,260.00 to $343,460.00.'. Upon a Roll-Call Vote being taken, the vote was: Aye: 8 Nay: 0.
The motion Carried 8 - 0
   
Lawrence Sykes     Yes
Sheila Greenwald     Yes
Rosemarie Linton     Yes
Dr. John Castanaro     Yes
Gail Burns     Yes
Dr. Rosalba Corrado Del Vecchio     Yes
Rev. Steve Lopez     Yes
Kevin Cacace     Yes