17.13 AWARD of CAPITAL Fund Construction Contract for Bid No. 6302A HVAC Work, CONTRACT 3 OF 4, CIP10732 “Restoration of Envelope, Security, and Site, Parking” at School 30 to Joe Lombardo Plumbing & Heating of Rockland, Inc. for the amount of $41,800.00 for a term of 365 calendar days.
|
District Goals:
|
|
Enclosure
|
|
File Attachment:
|
|
Rationale:
|
This resolution is to grant the administration the authority to enter into contract as described above. In compliance with General Municipal Law 103, this contract was let for public and bids were opened in public and read aloud on December 14, 2018. Bids were examined and all due diligence observed in determining the lowest responsive and responsible bidder. A total of 2 bids were received with the highest bid at $68,888. The work was designed by Greenman-Pedersen, Inc. who estimated Contract 2 work be $35,000. After interviewing the apparent low bidder and confirming that they understood the scope of work, bids were found to be correct, and references checked the architect and Schools Facilities Management is recommending award of this project to Joe Lombardo Plumbing & Heating of Rockland, Inc. for the amount of $41,800. This scope of CONTRACT 3 of 4, HVAC work includes the installation of a new split AC Unit serving the school’s IT Closet and replacement of existing AC window units with new AC units required for the new windows. The overall scope of work for CIP10732 includes but is not be limited to: the replacement of all windows,(including new shades) exterior and entrance vestibule doors, high tech security system and site work including 91 additional parking spaces in new and expanded parking lots. Overall project cost is roughly $6.8 million.
|
Funding:
|
B5530CP110732.101438.B2203, $20,000.00, LCBF B5530CP110732.B18C01.B2203A1620, $21,800.00, LCBF
|
Resolution:
|
Ladies and Gentlemen: WHEREAS: bids were issued for public advertisement and opened on December 14, 2018 in compliance with General Municipal Law for Bid No. 6302A HVAC Work, CONTRACT 3 OF 4 for the “Restoration of Envelope, Security, and Site, Parking” at School 30 Project No. 10732, and WHEREAS: such bids were duly examined and as a result of this examination of the bids submitted, the administration has determined that Joe Lombardo Plumbing & Heating of Rockland, Inc., is the lowest responsive and responsible bidder with a bid of $41,800.00. NOW THEREFORE BE IT RESOLVED: that Bid No. 6302A HVAC CONSTRUCTION Work, Contract 3 of 4, for Project No. 10732 “Restoration of Envelope, Security, and Site, Parking” at School 30 to Joe Lombardo Plumbing & Heating of Rockland, Inc., 321 Spook Rock Road, Suite 109A Suffern, NY 10901 in an amount not to exceed $41,800.00 for a term of 365 calendar days.
|
Approvals:
|
Recommended By:
|
Signed By:
|
|
John Carr - Executive Director
|
|
Signed By:
|
|
Lee Pavone - Mechanical Engineer
|
|
Signed By:
|
|
Finance Department - Finance Reviewer
|
|
Signed By:
|
|
Tom Collich - Purchasing Director
|
|
Signed By:
|
|
Elizabeth Janocha - Deputy Commissioner
|
|
Signed By:
|
|
John Liszewski - Commissioner
|
|
Signed By:
|
|
Matthew Gallagher - Corporation Counsel
|
|
Signed By:
|
|
Dr._Andrea_S. Coddett - Deputy Superintendent
|
|
Signed By:
|
|
Dr. Edwin M. Quezada - Superintendent of Schools
|
|
|
|
Vote Results:
|
Original Motion | Member Kevin Cacace Moved, Member Dr. Rosalba Corrado Del Vecchio seconded to approve the Original motion 'Ladies and Gentlemen: WHEREAS: bids were issued for public advertisement and opened on December 14, 2018 in compliance with General Municipal Law for Bid No. 6302A HVAC Work, CONTRACT 3 OF 4 for the “Restoration of Envelope, Security, and Site, Parking” at School 30 Project No. 10732, and WHEREAS: such bids were duly examined and as a result of this examination of the bids submitted, the administration has determined that Joe Lombardo Plumbing & Heating of Rockland, Inc., is the lowest responsive and responsible bidder with a bid of $41,800.00. NOW THEREFORE BE IT RESOLVED: that Bid No. 6302A HVAC CONSTRUCTION Work, Contract 3 of 4, for Project No. 10732 “Restoration of Envelope, Security, and Site, Parking” at School 30 to Joe Lombardo Plumbing & Heating of Rockland, Inc., 321 Spook Rock Road, Suite 109A Suffern, NY 10901 in an amount not to exceed $41,800.00 for a term of 365 calendar days.'. Upon a Roll-Call Vote being taken, the vote was: Aye: 7 Nay: 0 Abstain: 1. | The motion Carried 7 - 0 | | | Judith_Ramos Meier | Yes | Rev. Steve Lopez | Yes | Pasquale Mondesando | Yes | Edgar Santana | Abstain | Andrea Brown | Yes | Dr._Ammir Rabadi | Yes | Dr. Rosalba Corrado Del Vecchio | Yes | Kevin Cacace | Yes | |
|
|
|
|
|
|