Review Agenda Item
Meeting Date: 11/20/2018 - 7:00 PM
Category: SCHOOL FACILITIES MANAGEMENT
Type: Action
Subject: 18.10 CHANGE ORDER 1 (CREDIT) for CAPITAL Contract 2018-00000235, CIP10809, “109 Oak Street Play Area Project" at ENRICO FERMI SCHOOL to Peter J. Landi, Inc., for a credit in the amount of $23,785.00, decreasing the contract amount from $333,000.00 to $309,215.00.
District Goals:
Enclosure
File Attachment:
2018-00000235_PeterJLandi_109OakSt.pdf
RES 16.7 9-19-2017.pdf
CO Log .pdf
Rationale: A change order is a written agreement between the District and its contractor to change a building construction contract. They add to, delete from, or otherwise alter the work and/or progress schedule in the contract bid documents. CO’s are caused by any of three situations that can arise on a project: unforeseen conditions, design errors and omissions and owner directed extra work.

This contract was designed in house saving the cost of a design consultant and allowing for a compressed time schedule. However, as anticipated, more field editing was required. Schedule and budget targets were met.

There were roughly $10,000 in unforeseen conditions and another $29,115 in added owner directed work. This is offset by the built in contingency account of $25,000 and the deletion of $29,000 in un-needed contract earth work yielding a credit to the account of $23,785.00.
Funding: B5545CP110809.B17C01.B2206A1620 Local Capital Bond Fund
Resolution: Ladies and Gentlemen:

WHEREAS by Resolution Board Item No. 16.7 at the Board of Trustees stated meeting on September 19, 2017, contract No. 2018-00000235 was recommended for award to Peter J. Landi, Inc., 13 Bradhurst Avenue, Hawthorne, NY 10532 and,

WHEREAS: in the course of executing the contracted work it was determined that additional allowance and unit bid price work was not required to be performed for a credit in the amount of $23,785.00, decreasing the overall cost of the contract from $333,000.00 to $309,215.00.

NOW THEREFORE BE IT RESOLVED: That the Superintendent of Schools is hereby authorized to issue Change Order 1 to Contract 2018-00000235, Construction Contract, Project No. 10809 “109 Oak Street Play Area Project " at ENRICO FERMI SCHOOL to Peter J. Landi, Inc. for a CREDIT in the amount of $23,785.00 decreasing the contract amount from $333,000.00 to $309,215.00.
Approvals:
Recommended By:
Signed By:
John Carr - Executive Director
Signed By:
Tom Collich - Purchasing Director
Signed By:
Finance Department - Finance Reviewer
Signed By:
Elizabeth Janocha - Deputy Commissioner
Signed By:
John Liszewski - Commissioner
Signed By:
Matthew Gallagher - Corporation Counsel
Signed By:
Dr._Andrea_S. Coddett - Deputy Superintendent
Signed By:
Dr. Edwin M. Quezada - Superintendent of Schools
Vote Results:

Original Motion
Member Dr._Ammir Rabadi Moved, Member Pasquale Mondesando seconded to approve the Original motion 'Ladies and Gentlemen:

WHEREAS by Resolution Board Item No. 16.7 at the Board of Trustees stated meeting on September 19, 2017, contract No. 2018-00000235 was recommended for award to Peter J. Landi, Inc., 13 Bradhurst Avenue, Hawthorne, NY 10532 and,

WHEREAS: in the course of executing the contracted work it was determined that additional allowance and unit bid price work was not required to be performed for a credit in the amount of $23,785.00, decreasing the overall cost of the contract from $333,000.00 to $309,215.00.

NOW THEREFORE BE IT RESOLVED: That the Superintendent of Schools is hereby authorized to issue Change Order 1 to Contract 2018-00000235, Construction Contract, Project No. 10809 “109 Oak Street Play Area Project " at ENRICO FERMI SCHOOL to Peter J. Landi, Inc. for a CREDIT in the amount of $23,785.00 decreasing the contract amount from $333,000.00 to $309,215.00.'. Upon a Roll-Call Vote being taken, the vote was: Aye: 5 Nay: 0 Abstain: 1.
The motion Carried 5 - 0
   
Dr._Ammir Rabadi     Yes
Edgar Santana     Abstain
Andrea Brown     Yes
Dr. Rosalba Corrado Del Vecchio     Yes
Pasquale Mondesando     Yes
Rev. Steve Lopez     Yes