Type: Action
Subject: 16.7 Assignment of CAPITAL FUND, Design Consulting Services CIP 10881, “Saunders High School HVAC Upgrades” RFP#420-19-18 to LiRo Engineers, Inc. under a standing requirements contract No. 618430 in an amount not to exceed $92,950.00 for a term of 365 calendar days.
District Goals:
Enclosure
File Attachment:
E&R Proposal.pdf
LiRo- YPS Saunders HS MEP Proposal final.pdf
Rationale: Via Resolution 17.6 at their stated meeting on March 16, 2016 the Board of Trustees awarded requirements contract to LiRo Engineers, Inc. for an amount now totaling and not to exceed $1.0 million. The was amended once via Res 20.21 on April 14, 2019 to extend the terms by 24 months with no change to the funding.

This resolution assigns the subject task of in response to RFP 420-19-18 to LiRo Engineers, Inc. under the standing requirements contract 618430 via a new purchase order.

RFP 420-19-18 was issued on August 28, 2019 to two A/E Environmental firms with good design experience currently under requirements contracts with the District. Responses were opened on September 16.

Liro is being recommended for this task because of their size, experience, familiarity with the building and 3D modelling. E&R is also very suitable to the task but has just been awarded two other sizable projects.

Liro is slightly lower priced at $42,500 plus $50,000 for District authorized reimbursable expenses such as inspection equipment, sampling and testing. E&R submitted a fee of $45,000 plus the $50,000 for reimbursable expenses.

The task is to provide Architectural/Engineering/Environmental services for the review/inspection and design of HVAC upgrades at the Saunders High School up to the sketch plan level of detail.
Funding: B5764CP110881.B18C01.B2046A1620 $21,721.55 Local Capital Bonded Fund
B5764CP110881.B19C02.B2046A1620 $71,228.45 Local Capital Bonded Fund
Resolution: Ladies and Gentlemen:

WHEREAS: under Resolution 17.6 at the stated meeting on March 16, 2016, the Board of Education authorized the award of requirements based, Environmental Consulting Services Contract No. 618430 contract to LiRo Engineers, Inc. in response to District RFQ317 “Environmental Consulting Services for the School Facilities Management Department” for an amount not to exceed $1 million, and

WHEREAS: work as defined under that contract is the task is to provide Architectural/Engineering services for the review/inspection and design of HVAC Upgrades at the Saunders High School for the capital project 10881 “Saunders High School HVAC Upgrades” RFP # 420-19-18 issued August 28, 2019; and

WHEREAS: the response by LiRo Engineers, Inc. to a request for a proposal issued by the Facilities Department to be deemed most advantageous to the District at a cost in the amount of $92,950.00.

NOW THEREFORE BE IT RESOLVED: That the Superintendent of Schools is hereby authorized to assign LiRo Engineers, Inc., Three Aeriel Way, Syosset, NY 11791 to the task of providing professional Architectural/Environmental Consulting Services for CIP 10881 “Saunders High School HVAC Upgrades” under contract 618430 in an amount not to exceed $92,950.00. Term is for 365calendar days.
Approvals:
Recommended By:
Signed By:
John Carr - Executive Director
Signed By:
Finance Department - Finance Reviewer
Signed By:
Tom Collich - Purchasing Director
Signed By:
Elizabeth Janocha - Deputy Commissioner
Signed By:
John Liszewski - Commissioner
Signed By:
Matthew Gallagher - Corporation Counsel
Signed By:
Dr._Andrea_S. Coddett - Deputy Superintendent
Signed By:
Dr. Edwin M. Quezada - Superintendent of Schools
Vote Results:

Original Motion
Member Kevin Cacace Moved, Member Abdool H. Jamal seconded to approve the Original motion 'Ladies and Gentlemen:

WHEREAS: under Resolution 17.6 at the stated meeting on March 16, 2016, the Board of Education authorized the award of requirements based, Environmental Consulting Services Contract No. 618430 contract to LiRo Engineers, Inc. in response to District RFQ317 “Environmental Consulting Services for the School Facilities Management Department” for an amount not to exceed $1 million, and

WHEREAS: work as defined under that contract is the task is to provide Architectural/Engineering services for the review/inspection and design of HVAC Upgrades at the Saunders High School for the capital project 10881 “Saunders High School HVAC Upgrades” RFP # 420-19-18 issued August 28, 2019; and

WHEREAS: the response by LiRo Engineers, Inc. to a request for a proposal issued by the Facilities Department to be deemed most advantageous to the District at a cost in the amount of $92,950.00.

NOW THEREFORE BE IT RESOLVED: That the Superintendent of Schools is hereby authorized to assign LiRo Engineers, Inc., Three Aeriel Way, Syosset, NY 11791 to the task of providing professional Architectural/Environmental Consulting Services for CIP 10881 “Saunders High School HVAC Upgrades” under contract 618430 in an amount not to exceed $92,950.00. Term is for 365calendar days.'. Upon a Roll-Call Vote being taken, the vote was: Aye: 9 Nay: 0.
The motion Carried 9 - 0
   
Judith_Ramos Meier     Yes
Rev. Steve Lopez     Yes
Kevin Cacace     Yes
Andrea Brown     Yes
Dr._Edward Fergus     Yes
Abdool H. Jamal     Yes
Dr._Ammir Rabadi     Yes
Dr. Rosalba Corrado Del Vecchio     Yes
Dr. John Castanaro     Yes