Agenda Item
Meeting Date:
11/20/2018 - 7:00 PM  
Category:
SCHOOL FACILITIES MANAGEMENT  
Type:
Action  
Subject:
18.6 SECOND AMENDMENT TO CAPITAL FUNDED Contract 618507 for Professional Construction Management Services on a Requirements Basis to Savin Engineers, PC, in the amount of $1,000,000.00 increasing the total contract to $3,000,000.00 and extending the term for an additional 12 months.  
District Goals:
 
Enclosure:
 
File Attachment:
Cont 618507_Savin.pdf
Res 16.12 1-17-18.pdf
Res 17.7 3-18-16.pdf
Res 20.15 4-18-18.pdf
Res 22.31 6-19-2018.pdf
 
Rationale:
This is to amend a contract awarded to Savin via Board Resolution Item 17.7 dated March 16, 2016 and amended via Board Resolution 22.31 dated June 19, 2018. The resolutions provided up to $2 million for CM work and contract expiring on April 30, 2019. This resolution is to increase the amount of the contract to $3 million to cover an added $770,740.00 in CM work to be assigned to Savin under separate assignment resolutions for 2019 summer CIP and extending the contract term from April 30, 2019 to April 29, 2020. See attached contract summary.  
Funding:
CAPITAL BOND FUNDS ON A PROJECT BY PROJECT BASIS.  
Resolution
WHEREAS: The District has a need for on-going professional construction management services for the maintenance and improvement of its physical plant, and

WHEREAS: such services have been duly solicited in compliance with NYS Municipal Law 104B and the City of Yonkers procurement policy through the issuance of the publicly advertised request for proposal RFP316 “Construction Management Services for the School Facilities Management Department”, and

WHEREAS: Via Resolution 17.7 at their stated meeting on March 16, 2016 the Board of Trustees awarded requirements contract 618507 to Savin Engineers PC , for an amount not to exceed $1 million is response to RFQ316 and,
WHEREAS: Via Resolution 22.31 at their stated meeting on June 19, 2018 the Board of Trustees amended the requirements contract 618507 to Savin Engineers PC , for an amount not to exceed $2 million and extend the contract for an additional 12 months,
WHEREAS: additional tasks beyond the current contract amount and term are required by the District from Savin Engineers, PC, and
WHEREAS: per provisions in the contract, the contract term is to be extend by mutual consent of the parties by 12 additional months to a new term completion date of April 29, 2020, and

WHEREAS: work in value beyond the original contract limit of $2 million is required, and

WHEREAS: the value of this added work is estimated to be $1 million.

NOW THEREFORE BE IT RESOLVED: That the Superintendent of School be authorized to amend Contract 618507 for Professional Construction Management Services on a Requirements Basis to Savin Engineers, PC to increase the available limit by $1,000,000.00 to $3,000,000.00 and extend the term to April 29, 2020 per RFQ316 “Construction Management Services for the School Facilities Management Department”
 
Approvals:
Recommended By:
Signed By:
Finance Department - Finance Reviewer
Signed By:  
Tom Collich - Purchasing Director
Signed By:  
Elizabeth Janocha - Deputy Commissioner
Signed By:  
John Liszewski - Commissioner
Signed By:  
Matthew Gallagher - Corporation Counsel
Signed By:  
Dr._Andrea_S. Coddett - Deputy Superintendent
Signed By:  
Dr. Edwin M. Quezada - Superintendent of Schools
 
Vote Results:

Original Motion
Member Dr._Ammir Rabadi Moved, Member Pasquale Mondesando seconded to approve the Original motion 'WHEREAS: The District has a need for on-going professional construction management services for the maintenance and improvement of its physical plant, and

WHEREAS: such services have been duly solicited in compliance with NYS Municipal Law 104B and the City of Yonkers procurement policy through the issuance of the publicly advertised request for proposal RFP316 “Construction Management Services for the School Facilities Management Department”, and

WHEREAS: Via Resolution 17.7 at their stated meeting on March 16, 2016 the Board of Trustees awarded requirements contract 618507 to Savin Engineers PC , for an amount not to exceed $1 million is response to RFQ316 and,
WHEREAS: Via Resolution 22.31 at their stated meeting on June 19, 2018 the Board of Trustees amended the requirements contract 618507 to Savin Engineers PC , for an amount not to exceed $2 million and extend the contract for an additional 12 months,
WHEREAS: additional tasks beyond the current contract amount and term are required by the District from Savin Engineers, PC, and
WHEREAS: per provisions in the contract, the contract term is to be extend by mutual consent of the parties by 12 additional months to a new term completion date of April 29, 2020, and

WHEREAS: work in value beyond the original contract limit of $2 million is required, and

WHEREAS: the value of this added work is estimated to be $1 million.

NOW THEREFORE BE IT RESOLVED: That the Superintendent of School be authorized to amend Contract 618507 for Professional Construction Management Services on a Requirements Basis to Savin Engineers, PC to increase the available limit by $1,000,000.00 to $3,000,000.00 and extend the term to April 29, 2020 per RFQ316 “Construction Management Services for the School Facilities Management Department”'. Upon a Roll-Call Vote being taken, the vote was: Aye: 5 Nay: 0 Abstain: 1.
The motion Carried 5 - 0
   
Dr. Rosalba Corrado Del Vecchio     Yes
Dr._Ammir Rabadi     Yes
Andrea Brown     Yes
Rev. Steve Lopez     Yes
Edgar Santana     Abstain
Pasquale Mondesando     Yes