20.12 AWARD of CAPITAL Fund Construction Contract 4 of 5 Bid No. 6326 PLUMBING Work, CIP10813 “Restoration of Windows, Doors, Interiors, Security, Site and Asbestos Abatement” at School 5 to Pearl River Plumbing Heating & Electric, Inc. (d/b/a Bertussi’s), for the amount of $267,425.00 for a term of 365 calendar days. |
|
|
District Goals:
|
|
Enclosure:
|
|
File Attachment:
|
|
Rationale:
|
This resolution is to grant the administration the authority to enter into contract as described above. In compliance with General Municipal Law 103, bids were let and opened in public March 13, 2019. Bids were examined and all due diligence observed in determining the lowest responsive and responsible bidder. Pearl River Plumbing Heating & Electric, Inc. (d/b/a Bertussi’s) was the sole bidder for the plumbing contract bid. The work was designed by Greenman-Pedersen, Inc. who estimated Contract 4 work be $279,707. After interviewing the apparent low bidder and confirming that they understood the scope of work, bids were found to be correct, and the work history with the District, GPI, Savin Engineers and School Facilities Management are recommending award of this contract to Bertussi for the amount of $267,425.00, excluding bid Alternate 1. This scope of CONTRACT 4 of 5, PLUMBING includes the replacement of plumbing fixtures and related piping for select boys & girl’s gang bathrooms and limited sprinkler piping alterations required for the Cafeteria renovation. Overall, CIP10813 includes but is not be limited to: new window & shades, select exterior door replacement, new PA system, cafeteria and select toilet room renovation, new high tech security system; exterior building lighting improvements; site improvements, gym HVAC & lighting and requisite asbestos abatement. The overall cost of this project is roughly $5 million. The original bid included alternates for further renovation of the gymnasium including drainage, flooring, lighting, paint, wall padding and gym equipment. These alternates were rejected because they are beyond the reach of current budgeting. |
|
|
Funding:
|
|
Resolution
|
Ladies and Gentlemen: WHEREAS: bids were issued for public advertisement and opened on March 13, 2019 in compliance with General Municipal Law for Bid No. 6326 PLUMBING Work, CONTRACT 4 OF 5 for the “Restoration of Windows, Doors, Interiors, Security, Site and Asbestos Abatement” at School 5 Project No. 10813, and WHEREAS: such bids were duly examined and as a result of this examination of the bids submitted, the administration has determined that Pearl River Plumbing Heating & Electric, Inc. (d/b/a Bertussi’s), is the lowest responsive and responsible bidder with a bid of $267,425.00. NOW THEREFORE BE IT RESOLVED: that Bid No. 6326 PLUMBING, Contract 4 of 5, for Project No. 10813 “Restoration of Windows, Doors, Interiors, Security, Site and Asbestos Abatement” at School 5 Project to Pearl River Plumbing Heating & Electric, Inc. (d/b/a Bertussi’s), 60-70 Dexter Plaza, Pearl River, NY 10965 in an amount not to exceed $267,425.00 for a term of 365 calendar days. |
|
|
Approvals:
|
Recommended By: |
Signed By: |
|
John Carr - Executive Director |
|
Signed By: |
|
Tom Collich - Purchasing Director |
|
Signed By: |
|
Finance Department - Finance Reviewer |
|
Signed By: |
|
Elizabeth Janocha - Deputy Commissioner |
|
Signed By: |
|
John Liszewski - Commissioner |
|
Signed By: |
|
Matthew Gallagher - Corporation Counsel |
|
Signed By: |
|
Dr._Andrea_S. Coddett - Deputy Superintendent |
|
Signed By: |
|
Dr. Edwin M. Quezada - Superintendent of Schools |
|
|
|
|
|
Vote Results:
|
Original Motion | Member Kevin Cacace Moved, Member Pasquale Mondesando seconded to approve the Original motion 'Ladies and Gentlemen: WHEREAS: bids were issued for public advertisement and opened on March 13, 2019 in compliance with General Municipal Law for Bid No. 6326 PLUMBING Work, CONTRACT 4 OF 5 for the “Restoration of Windows, Doors, Interiors, Security, Site and Asbestos Abatement” at School 5 Project No. 10813, and WHEREAS: such bids were duly examined and as a result of this examination of the bids submitted, the administration has determined that Pearl River Plumbing Heating & Electric, Inc. (d/b/a Bertussi’s), is the lowest responsive and responsible bidder with a bid of $267,425.00. NOW THEREFORE BE IT RESOLVED: that Bid No. 6326 PLUMBING, Contract 4 of 5, for Project No. 10813 “Restoration of Windows, Doors, Interiors, Security, Site and Asbestos Abatement” at School 5 Project to Pearl River Plumbing Heating & Electric, Inc. (d/b/a Bertussi’s), 60-70 Dexter Plaza, Pearl River, NY 10965 in an amount not to exceed $267,425.00 for a term of 365 calendar days.'. Upon a Roll-Call Vote being taken, the vote was: Aye: 6 Nay: 0 Abstain: 1. | The motion Carried 6 - 0 | | | Kevin Cacace | Yes | Andrea Brown | Yes | Dr. Rosalba Corrado Del Vecchio | Yes | Pasquale Mondesando | Yes | Edgar Santana | Abstain | Judith_Ramos Meier | Yes | Rev. Steve Lopez | Yes | |
|
|
|
|
|
|