Subject:
16.3 Amendment to 17.2 Ceridian – Month to Month Extension  
District Goals:
Goal 1
To educate all students for academic excellence.
 
Enclosure:
 
File Attachment:
Ceridian Amendment - Info for Resolution - June 2018.docx
Ceridian BOCS - Amendment.xlsx
 
Rationale:
Data Processing Department – GML104
Contractor – Ceridian
Term – July 1, 2017 – June 30, 2018
Amount of Subscription – $26,375.00
Scope - The purpose of this resolution is to amend Board Report 16.2, Ceridian – 2017-2018 Month to Month Extension, which the Board of Trustees approved on October 18, 2017 (Original contract 2018-00000256 and original BOCS approval date 10/19/2017. This amendment is intended to increase the amount of the agreement by $26,375.00 in order to cover the unforeseen increased cost of projects related the Payroll/HR system throughout the 2017-2018 school year. The projects being covered will be or have been completed by the end of the 2017-2018 school year. These are non-recurring expenses and going forward into 2018-2019 we do not expect any overages on projects that may be needed throughout the upcoming school year.
 
Funding:
450-5163-100000-1680-B2300 (2017-2018
Contractual Account – Local Funds)
 
Resolution
WHEREAS the Yonkers Public Schools is seeking approval to amend the Ceridian Month to Month agreement, Board Report 16.2, dated October 18, 2017, and,

WHEREAS this amendment will increase the amount of the agreement by $26,375 bringing the total cost for the 2017-2018 school year to $626,375.00, and,

WHEREAS the increase is necessary to cover the costs related to unforeseen overages for projects that have occurred throughout the 2017-2018 school year. These costs are non-recurring and are not expected during the upcoming school year.

NOW THEREFORE BE IT RESOLVED: That the Superintendent of Schools is hereby authorized to amend the 2017-2018 agreement with Ceridian to increase the amount by $26,375.00 bringing the total cost for the contract to $626,375.00.
 
Approvals:
Recommended By:
Signed By:
Carla B. Collins - Executive Director
Signed By:  
Bob Cacace - Commissioner
Signed By:  
Cheryl Green - Deputy Commissioner Dept. of Information Technology
Signed By:  
Tom Collich - Purchasing Director
Signed By:  
Finance Department - Finance Reviewer
Signed By:  
Dr. Fenix Arias - Manager of Administration
Signed By:  
Elizabeth Janocha - Deputy Commissioner
Signed By:  
John Liszewski - Commissioner
Signed By:  
Matthew Gallagher - Corporation Counsel
Signed By:  
Dr._Andrea_S. Coddett - Deputy Superintendent
Signed By:  
Dr. Edwin M. Quezada - Superintendent of Schools
 
Vote Results:

Original Motion
Member Dr. Rosalba Corrado Del Vecchio Moved, Member Pasquale Mondesando seconded to approve the Original motion 'WHEREAS the Yonkers Public Schools is seeking approval to amend the Ceridian Month to Month agreement, Board Report 16.2, dated October 18, 2017, and,

WHEREAS this amendment will increase the amount of the agreement by $26,375 bringing the total cost for the 2017-2018 school year to $626,375.00, and,

WHEREAS the increase is necessary to cover the costs related to unforeseen overages for projects that have occurred throughout the 2017-2018 school year. These costs are non-recurring and are not expected during the upcoming school year.

NOW THEREFORE BE IT RESOLVED: That the Superintendent of Schools is hereby authorized to amend the 2017-2018 agreement with Ceridian to increase the amount by $26,375.00 bringing the total cost for the contract to $626,375.00.'. Upon a Roll-Call Vote being taken, the vote was: Aye: 7 Nay: 0.
The motion Carried 7 - 0
   
Kevin Cacace     Yes
Dr. Rosalba Corrado Del Vecchio     Yes
Edgar Santana     Yes
Andrea Brown     Yes
Pasquale Mondesando     Yes
Judith_Ramos Meier     Yes
Rev. Steve Lopez     Yes